Is London Stadium worth spiralling cost?

Olympic stadium £486m Paid by Government Conversion cost £274m Paid by Government, with £40m from Newham Council, £15m from West Ham Total cost when West Ham moved in 2016 £760m Losses by E20 Stadium per year since, at an average £25m a year £125m Cost of building and running it to date. Mostly paid by public £885m If E20 losses are maintained at £20m a year, stadium will have cost £1bn by 2029.